Before Construction Begins:
Pick out the house plan you want with builder.
-
Find a suitable lot for building with builder.
-
Walk the lot to check for elevations, drainage, feasibility of excavation,
etc...
-
Make sure that the house will fit on the lot within the proper guidelines
set by the community.
-
Determine where to set the house on the lot and which trees to keep
and which trees to remove.
-
Get a core soil sample done to determine the type of foundation
is required for your lot.
-
Sit down with builder and go over detailed specification sheets of your
home.
-
Meet with builder to go over quote and to refine the details to
fit into your budget.
-
Sign contract with builder.
-
Make a final walk of property to make sure the house location is
correct and that the trees to be removed are properly marked.
Construction Begins:
Excavate Property (3-4 days):
Clear out entire area where house will be located on lot.
Remove all trees and shrubs that were marked for removal.
Bring in fill dirt (if necessary).
Level house location
Prepare house location for foundation (2-3 weeks):
Survey the site (ongoing).
Place form boards.
Drill and fill piers (if necessary).
Install all underground plumbing.
Prepare site for concrete.
Install post-tension cables.
Pour foundation.
Clean up area and remove form boards.
Framing (2-3 weeks):
House plans laid out on foundation.
All framing done.
Roof decking installed.
Windows and outside doors installed.
Roofing Installed (2-4 days):
Install felt or waterproofing.
Install roof.
Insulation, Stucco, Stone, and Brick (3-4 weeks):
Outside of house will be finished with the product specified by the
home
owner.
Outside trim.
Install fireplace.
Spray or install Insulation.
Electrical, Alarm System, Home Entertainment Center, and Network
wiring (2-3 weeks):
Install all electrical wiring and boxes.
Install all alarm system wiring.
Install all speaker & intercom wiring.
Install all computer cables.
Install Television cables.
Drywall (2 weeks):
All Sheetrock installed.
Tape and bedding installed and sanded.
Apply texture.
Cabinet installation (3 days):
Install custom cabinets.
Trim (4-5 weeks):
Interior Doors, moulding, and shelving installed.
Install garage doors
Painting (2 weeks):
Walls, trim, and cabinets painted, and stained.
Electrical, plumbing, and driveway / sidewalks (1-2 weeks):
Lights, fixtures, switches, hook up, sinks, toilets, and water
heaters installed.
Sidewalk, driveway, and pads poured.
Flooring (2 weeks):
Carpet and/or wood, and tile installed per house specifications.
Final outside grading, sprinkler system, landscaping, hydro-mulch,
or
sod installed (1 week).
Prepare lot for proper drainage, gutters installed. Clear away remaining debris and brush,
install landscaping and grass per specifications.
Appliances installed (1 day)
Paint touch up, and final make ready (1 week).